TransportationThree Oaks Parkway
(May 2006 EDR) In order
for the residents of Southwest Florida to have a third north-south
arterial corridor extending from Naples to Ft Myers three projects
need to be completed. They are (from south to north):
- The segment of Imperial Street from Bonita Beach Road to East
Terry Street,
- The segment of Three Oaks Parkway from East Terry Street to just
south of Coconut Road in The Brooks, and
- The segment of Three Oaks Parkway from Corkscrew Road to Alico
Road.

Imperial from Bonita Beach to East Terry Street
This segment involves construction of a new four lane road that
crosses over the Imperial River. It was recently bid with the
winning bids being about $6 million over budget. The City of Bonita
Springs recently voted to provide the additional funding. The County
is now in the process of finalizing the contract with Posen
Construction, the Michigan firm that won the contract. Once that
step is completed, construction of the roadway can begin. Completion
is expected in late 2007 or January 2008.
Three Oaks Parkway from East Terry Street to the Brooks
(Coconut Road)
This four mile segment is also new construction of a four lane
highway. On May 8th construction was begun with the groundbreaking
three days later, on the 11th. This segment is also being
constructed by Posen Construction, the Michigan firm that is new to
our market, and claims that it has an excellent record of finishing
its projects on time. The segment is planned to be opened for use in
January 2008.
Three Oaks Parkway from Corkscrew Road to Alico Road
The contract for
this
segment was awarded to Posen Construction in October 2006. Posen
began construction in early December. When complete this segment
will permit motorists to travel from Alico Road in Ft Myers to Radio
Road in Naples upon a continuous 4 lane highway.
Estero Development Reports
Mar. 2008 -
Progress Update EDR
December 2007 - Brief Progress Report
March 2007 -
Three Oaks Parkway from Coconut Road to East Terry Street
December 2006 -
Three Oaks Parkway from Coconut Road to East Terry Street
November 2006 -
Update
October 2006 -
Coconut Road to East Terry Street
August 2006 -
Three Oaks/Imperial/Livingston Projects Status Report
May 2006 -
Three Oaks/Imperial/Livingston Projects Status Report
December 2005 -
County DOT Manager reports on Progress
November 2005 -
Supplemental State Road Funding Allocated to Three Oaks Parkway
May 2005 -
Funding Progress
| |
| |
|
|
|
|